50 Victoria Street, Christchurch

  • image 01
  • image 01
  • image 01
  • image 01
  • image 01
  • image 01

Value:

$4.5 million

Construction Period

August 2013 - March 2014

Details:

50 Victoria Street was the second design-build project completed for Countrywide Group. Again utilizing the sister companies' (DHC Consulting Ltd for the structural design and D&H Steel Construction Ltd for the structural steel) capabilities Clearwater constructed the new office building comprising 1,200m² of office space over 400m² of hospitality area.

Scope of works included; detailed foundation excavation, structural steel and precast structure, three levels of suspended concrete floors, a sonafil membrane roof and curtain wall envelope to the Victoria Street frontage. Building services were let on a design-build basis with key subcontractors being managed by Clearwater to produce a fully co-ordinated design.

Clearwater worked with the client and ground floor tenant to ensure early hand-over of the ground floor to enable 'The Bog' to begin fit-out works, as early as possible, with the ultimate goal of having the business up and operational at the earliest possible date.