Project Details
- Construction
- Stage 1 – Basement parking and podium levels
- Stage 2 – 4 level office tower (4,000sqm)
- Early contractor involvement (ECI) – Clearwater offered up a number of Value Engineering options which assisted the client in ensuring a cost effective project was delivered
- Clearwater completed the foundations, basement and suspended floor concrete works with own direct labour
- Managed and co-ordinated other trades including excavation, piling, precast concrete, structural steel, curtain wall, aluminium composite panels and metal roof installation